Hengli Petrochemical (Dalian) New Materials Technology, constructed by CIMC Anruike Engineering Technology Co., Ltd., has

Release time:2025-03-26 09:57:52

The first 160000 cubic meter low-temperature concrete full capacity tank gas lift roof of Hengli Petrochemical (Dalian) New Materials Technology Co., Ltd., constructed by CIMC Anruike Engineering Technology Co., Ltd., has been successfully completed

 

On the morning of June 8, 2023, at 9:18:18 am, the first 160000 cubic meter (low-temperature propane/butane) concrete fully enclosed storage tank of Hengli Petrochemical (Dalian) New Material Technology Co., Ltd., constructed by CIMC Anruike Engineering Technology Co., Ltd. (referred to as "CIMC Engineering Technology"), achieved a complete success in gas lifting!


1.jpg 


The entire process of raising the roof took 2 hours and 18 minutes, and the arch was smoothly lifted by the sound of the blower blowing air. Starting from December 29, 2022, the pouring of concrete for the pier cap until the completion of this air lift roof, all parties involved in the construction worked together to overcome the unfavorable factors of the national epidemic at the beginning of the year. After working tirelessly day and night, the project team completed the milestone of the lifting in just 162 days, achieving the fastest construction speed of 160000 cubic meters of fully inclusive concrete storage tanks in the country, once again echoing the "constant force speed" of CIMC Engineering Technology.


2.jpg 


The inner diameter of the outer tank of this project's storage tank is 92 meters, equivalent to the diameter of a 250000 cubic meter storage tank. The lifting height is 32 meters, and the top weight is about 1300 tons. It is the largest concrete storage tank of CIMC Engineering Technology since its establishment. The successful completion of this air lift is another fruitful achievement of CIMC Engineering Technology in the field of low-temperature concrete full containment tank construction. With the continuous improvement of technology and operational methods, CIMC Engineering Technology has developed a complete set of low-temperature storage tank construction methods and project management models. In the future, the company will continue to increase its development efforts and technological investment in large-scale low-temperature storage tanks, further enhancing its competitiveness in the low-temperature field, and creating one high-quality project after another with first-class technical strength and service capabilities!


3.jpg 


One collaboration is trust, and another collaboration is quality. In 2019, CIMC Engineering Technology successfully put into operation a 50000 cubic meter low-temperature ethylene storage tank for the Dalian Hengli project. Today, CIMC Engineering Technology and the owner of Hengli Petrochemical have once again collaborated on the successful completion of the 160000 cubic meter low-temperature concrete full capacity tank gas lift, marking the official transition of the tank from early civil construction to internal tank installation and construction, laying a solid foundation for achieving the mechanical completion goal of the project on schedule. The two collaborations fully demonstrate CIMC Engineering Technology's excellent technical level and management capabilities in the field of low-temperature storage tanks, making it the best choice for the owner. The CIMC Engineering Technology Management Team will continue to be meticulous, carefully organized, and strictly constructed to assist in the smooth completion of the project, contributing the power of CIMC Engineering Technology to national energy construction and social livelihood.


Previous:The reserve amount has been increased from 7 days to 30 days! CIMC Anruike wins bid for Shenzhen Natural Gas Reserve and Peak shaving Reservoir

Next:hot wire! Ascend to the top and climb to the highest peak again

About Us

Introduction

Mission Vision

Corporate Milestones

Corporate Brochure

Accreditation Certificates

Business

Petrochemical Engineering

Storage & Transportation Engineering

Fine Chemicals Engineering

Cryogenic Storage & Transportation

Environmental Engineering

Natural Gas Infrastructure Engineering

Chemical Park Planning

Utility Systems Engineering

Contact Us

Recruitment phone:025-57050819

Recruitment Email:cet@cimc.com

Phone:025-57053029
Collaboration Email:
cet-marketing@cimc.com

Address: 7.No. 95, Yangcun 3rd Road, Dachang Subdistrict, Jiangbei New District, Nanjing City, Jiangsu Province, China

Common links

CIMC Group's official website:www.cimc.com

CIMC ENRIC:www.enricgroup.com

CIMC Enric Engineering Technology Co., Ltd. Copyright

Official WeChat Account